Pilgrim Stage Station Wind Park
Pilgrim Stage Station is one of 11 wind parks in the 183-MW Idaho Wind Partners project, the largest wind energy development effort in Idaho history. Pilgrim Stage Station is one of nine parks in the Bell Rapids cluster near Hagerman, Idaho.
| Year Completed | 2010 |
| Location | Twin Falls County near Hagerman, Idaho |
| Rated Capacity | 10.5 MW (equivalent to 2,300 homes powered annually) |
| Number of Turbines | 7 |
| Turbine Technology | GE 1.5 MW turbines |
| Power Off-Taker | Idaho Power |
| Construction Jobs | 175 for full 183-MW Idaho Wind Partners project |
| Permanent Jobs | 25 for full 183-MW Idaho Wind Partners project |
| Avoided Greenhouse Gas Emissions | 19,000 tons eCO2 per year (equivalent to taking 3,300 cars off the road annually) |